How do I have multiple predecessors for a task?? Help!

December 7, 2012 - 02:01 am
2 comment(s)

I have the same problem recently noted by another user.  How do I create a task and add multiple predecessors to it?  It will only let me add one predecessor - any attempt to add more gives me an error message.

2 Comments

February 19, 2013 - 23:58 pm

I have installed the latest version.

I have create four task: one, two, three, four

one - duration one day

two - 2 days

three 3 days

the fourth: one day

at the fourth task, in predecessor I wrote: 1;2;3

All works correctly: the fourth moves to the end