predecessor running parrel

February 5, 2014 - 15:36 pm
3 comment(s)

HI Team Libre'

 

Have a strange request .

doing a project where there is predecessor runinng 2 weeks and its succesor starting a day after inintiation but it only allows me to set the successor date after the predecesor is complete. is there a way to do this with link the the two

 

Regards Damain(Johannesburg South Africa.)

 

 

3 Comments

February 6, 2014 - 09:44 am

Yes, you can change the Finish Start default predecessor relationship  to a Start Start relationship with a 1 day delay.  That will work....

February 7, 2014 - 20:18 pm

Thank you kindly for your response ,

 

Was easily applied and even easier to just add ss to the predecessor number once located.

This software just continues to raise my expectations and from me and my whole team thank you Team Libre' for this. Great software :)

February 8, 2014 - 04:40 am

Thank you as well.... we generally only get email and notes when people are not happy.  We are very pleased with our progress but still have work to do.  It is nice to have you in the community and all the best with your projects!

 

Marc & Team