Discussion

Changing time unit

February 14, 2013 - 00:03 am
jeb
4 comment(s)

Hi everyboby

I'm a newby. I'm wondering if it is possible to change the time unit form day to week of month. For some quite long project a daily schedule is a nightmare to manage.

Cheers

4 Comments

February 20, 2013 - 02:12 am

Hey there,  your tasks is displaying the span over time and will overlap the non-working time.  We will have a future option to not span so it will visually display differently.  Your case is a bit unusual but lesser cases also show an extended bar....

In reply to by OB

October 8, 2013 - 17:01 pm

Hello,

 

On long projects, we need to overview all in only one page (synthetisis of the project).

It' necessary to dilate or to expand the time scale without to modify the size of the commentars or the name of the tasks.

It's another thing to optimize the size of document to print and to change the time scale.

How to change the time scale with the version 1.5.7?