  • Fabian36
    20 May 2013 - 21:41 by Fabian36

    Hello,

     

    is there a chance to add annotations to the gantt diagram?

    If not, it would be great to have such a feature, as it would benefit for the understanding of the chart.

    3 comment(s)
  • pedrojo
    17 May 2013 - 04:50 by pedrojo

    Hi everybody.

    In my project, I have only one task (TASK1), and I think it will last for 10 days.

    I assigned three resources to TASK1: Supervisor, Employee and a Diver.

    3 comment(s)
  • indigav
    16 May 2013 - 08:06 by indigav

    Possible Java replacement

    Is there any existing or  soon to be released Java alternative for ProjectLibre?

    I notice that LibreOffice is starting to replace Java with Python script. See here http://ask.libreoffice.org/en/question/10258/java-replacement-by-python-...

    With all the documented problems of Java security I would be happy to see this happen sooner rather than later.

    java
    1 comment(s)
  • raudione
    13 May 2013 - 14:14 by raudione

    latest version of ProjLibre on a Winows7 laptop. As I enter infomation (date, task name etc) i press Enter to go to the next line..nothing happens. Have to use the mouse to click into another cell.

    No issues in any other apps i use.

    1 comment(s)
  • Hezequias Vasconcelos
    10 May 2013 - 05:41 by Hezequias Vasco...

     

    Hello, What is needed to be a moderator in the Community ProjectLibre? Thanks.

    0 comment(s)
  • jollins
    10 May 2013 - 02:04 by jollins

    We are starting some big projects and need to be able to collaborate on a project in real time on multiple machines. Being able to add tasks and what not on the fly. As we are a small company we have to be flexable. is there any support for this? we have tried but the updates dont seem to reflect once saved.

    2 comment(s)
  • Bob1022
    7 May 2013 - 15:03 by Bob1022

    I am running Linux Mint with ProjectLibre. I am trying to change the workday time. I can get to the screen required and create a Special Calendar, but ProjectLibre will not accept revised start and finish times.

    UPDATE: I figured out that you have to define the days on your calendar that covers the duration of the project in order to be able to change the start and finish time. I then assign the new cendar to the resources that use it. However, now I cannot save the calendar with the revised start and finish times.  Help?

     

    Bob N

    3 comment(s)
  • ardsur
    30 Apr 2013 - 20:29 by ardsur

    How to add a picture to my account ?

     

    I see in my account this option. However it does not state the max size of the image, nor the minimum height ???

    I tried some images that are working in other forums and social media , but none was accepted.

     

    It would be nice to see the different avatars on the discussions rather than this present rather stiff looking gentlemen.

    account, picture
    2 comment(s)
  • lewisdw
    27 Apr 2013 - 03:12 by lewisdw

    Is it possible to create a recurring task in PL?  How?

    recurring, task
    2 comment(s)
  • AnxoM
    26 Apr 2013 - 05:26 by AnxoM

    Hi everybody

    This is my first contact with this community, so if I were wrong with this question plese inform me.