Hi

I've been using ProjectLibre for scheduling purposes. Under the calendar I could basically set up the working hours as 7 hrs. for a working day despite the timings 9:30-14:00 & 14:30-18:00 which reflect as 8 hrs working per day. Because I was couting off 1 hrs for various meetings so the team works for 7 hrs. Now it reflected against the tasks durations e.g., when I mentioned 8hrs of work estimate against a task it shows me 1.143 days however I have observed that start date time and end date time are not adjusted accordingly. Is there a way that the working hrs per day setting be referenced for calculating end datetime for a task given some estimates?

Best Regards

Pawan Rai