How to change Calendar Working days and Working time for all days.

June 3, 2013 - 20:03 pm
6 comment(s)

Hi all,

My working time is entirely different than default one which one has in Project Libre.

My working days are Monday to Saturday.

My Working Hours is 10:00-14:00 and 14:30 - 20:00

How can i change the above timings and saturday as working day in that.

Please help me on this.

thanks in advance.

Mahalingam.A

 

6 Comments

June 3, 2013 - 21:41 pm

Hello, 

Select the Project tab - Group Projects - Calendars.

 

Click the New button - Set the name of the calendar. Example: Working Hours. Click on the letter S which means Monday and set the time from 10:00 to 14:00 and then from 14:30 to 20:00 exactly as you need. Repeat this procedure for Tuesday, Wednesday, Thursday, Friday and Saturday. Select and set Sunday as clearance period. In options you can set the hours of work daily, weekly hours and days per month, at the end click OK. To set this as the default calendar in your project, click Project - Projects - click with the right mouse button and enter the Calendar field and then select the schedule created.  Hope this helps.

June 15, 2013 - 04:02 am

I have the same problem.  I've changed the calender, I've added other calenders, and still cannot change the default working hours.  It continues to start the working hours at 8:00, and we start at 7:00.  No matter what I try, it continues to enter 8:00 even if I manually change it to 7:00.  It was continually starting working hours at 2:00am, but not it's 8:00.  It's very annoying.Thanks in advance.

July 1, 2015 - 08:44 am

Hi All,

I am working on a project that has the duration of 9:00Am to 12:00 PM and then 12:30 PM to 5:06 PM.

I am unable to set this time in the Calendar of Project Libre. I have tried creating a new calander and entered the above time as 'Non-default working time'. This is simply not working. The tasks still shows the start time as 8:00 AM. I confirm that I am using the new calaendar.

Cheers,

gaurav

May 31, 2016 - 16:28 pm

The same problem exists still. In our country, for this industry area, standard working hours defined by union agreements are 08:00-16:00 with half hour mandatory lunch break in between. So there are 7.5 hours per day and 37.5 hours per week.

I have tried to set working hours on calendar, but ProjectLibre still calculates hours using its own default 08:00-17:00 schedule.

June 1, 2016 - 03:17 am

Hi there,

There are multiple calendars, Project/Task/Resource and there is the default calendar.  Have you checked to see if the project calenar is set properly?

October 19, 2016 - 17:35 pm

I'm finding that it's very sequence dependent ie if I set up a weekend to work before I assign the resource then they are working on the resource assignment sheet.  If however I change make the weekend working after the resource has been assigned they are not shown working at the weekend.  Is this a bug?  I'm going to try and find a work around.  Maybe removing and recreating the task and or the resource will work.  Any suggestions?

Stephen