Discussion

planned and actual value

March 18, 2014 - 20:53 pm
5 comment(s)
hello,
in project libre , how can i see the planned date and actual date for a work item in the gantt chart ? i want to see the progress information visually..
thanks a lot
serafettin

5 Comments

July 5, 2015 - 23:04 pm

The only way I can seem to enter actuals in ProjectLibre is to add the "work" & "duration"  columns to my GANTT chart and type values in there

Is there a better way? It's much easier in MS Project, which allows %complete to be added into "Task" dialogue

July 27, 2016 - 07:21 am

I want to be able to see where an item may be going over planned duration or planned work but say I have planned duration of 1 day and actual is 2 days it will default the actual back to planned of 1 day.

 

Why does this happen and how do I change.

 

Ms Project will auto adjust the duration and following tasks to suit which I am not really interested in but I need to see visually where I am going over per task.