Task durations

August 19, 2016 - 17:17 pm
0 comment(s)

Is it possible to assign whether a task duration is including weekends and others as exclude weekends? In my case, the workforce will work week days only. However, if I pour cement, it need 14 days to cure, So I need to include weekends in the cure period.