Discussion

Update Task issue

September 1, 2014 - 18:16 pm
dahms
2 comment(s)

ProjectLibre is great and I'm only having one issue. When I use "Update Tasks" and I enter the "Actual" Start date and time the "Original" Start date and time changes to the "Actual" start date and time I just updated. Is this a bug or am I doing something wrong?

2 Comments

September 4, 2014 - 13:08 pm

I am hoping this is user error but will not stipulate that as it could be a bug... can you send me the project file.  There  has occasionally been an issue..... what OS and Java version are you using ?