earned value

Discussion

How is BCWP calculated

3 comment(s)

How is BCWP, ACWP, BCWS calculated?

In ProjectLibre 1.5.3 on Ubuntu , I do the following:

1. Create task of 1 week
2. Assign it to a ressource with a salary of 10 euros per hour
3. Cost ends being 400
4. Save baseline in the default baseline
5. BCWS = 80 euros
6. Change % achevé (I belive this would be % done) to 10%
7. BCWP = 40 euros, ACWP = 40 euros
8. Change % done to 30%
9. BCWS = BCWP = ACWP = 80 euros

I would have expected
BCWS = 400 (same as cost)
BCWP = 120
ACWP = 120

Is this a known issue or is something in earned value theory escaping me?