Work

Discussion

Work contour

0 comment(s)

Hello everybody

I have a question about the calculation of the "Work" of task with respect to the work contour selected.

Example:

I have a task with "Fixed Work". I created the task with the "work contour "Flat". If I change the "work countour" afterwards to any other type e.g. to "front loaded" the "Work" will be reduced and I have to set the "Work" to the correct value again  manually.

Can anybody explain this behavior?

Kind regrads

 

Michael

Discussion

Struggling to apply multiple resources with different work commitment to one task

0 comment(s)

Dear All,

I am tryint to set up a task, which requires a total of 40 hours of week, which may spread over 10 days duration. I am using the "Fixed Work" type. All works well, until I start adding resources. Initially, can add all resources, but when I want to change their individual hours, the duration changes to the total hours accoding to the resources calendar. When I want to change this again to reflect that the actual work may be spread over two weeks, all goes haywire and I cannot spread the total work hours over the resouces as I deem fit. To make things worse, PL also insists during this process to change the default contrain type to "Start no earlier than", which I suspect is a bug.

Is this normal behaviour and I am using the software wrongly? If so, how would I do this best, e. g., setting up 3 different sub-tasks for each resource? Or shall I leave the "Duration" alone and add some "Lag" to any successor to reflect that this task can move flexibly within a certain time frame?

Thanks for your help

Tom

Discussion

Work and Duration

1 comment(s)

Hello,

I added the column "work" next to "duration". First is shown in hours, second in days. Is it possible to set both same? I prefer to work with days only. It is not very useful to work with thousend of hours if you want to set 100 or 200 days for a single task.

Thank you