1 | Setting a date to occur X number of days before another date | This should be simple, but I can't seem to make the following happen: I have a project plan for construction. The majority of the tasks follow in a linear fasion (dig the hole, then pour the foundation, then installl window well, then backfill). Those work fine. But I need a set of deadlines for ordering material. I want the deadline for ordering the window wells (for example) to be 5 days before backfill. So whatever date backfill works out to be, I want the window well order deadline to be 5 days before. How do I do this? |